On 10 November 2026, the Norwegian government announced that it will introduce measures to ensure the controlled growth of data centers in Norway and to ensure that they are as beneficial to society as possible. This includes the introduction of a licensing regime for data centers.

On the same day, Statnett (the transmission system operator in Norway) announced temporary suspensions which may prevent data centers from being connected to the grid until 1 August 2027.

The measures to be assessed by the government include:

  1. Prioritizing data centers that are beneficial to society (defense, health, communication, etc.)

  2. Regulatory amendments enabling Statnett to set conditions for secure grid connection

  3. Prioritization of critical societal consumption for which grid companies must reserve capacity

  4. Modernization of grid companies’ obligation to connect customers

  5. How stakeholders will cover a greater share of the costs imposed on the grid – both investments in new grid infrastructure and operations

  6. How the data center industry can contribute to the development of power generation, including offshore wind and gas-fired power plants with carbon capture and storage (CCS)

  7. Models for state ownership in particularly socially beneficial data center projects

Statnett, for its part, announced:

  1. a temporary suspension of new connection reservations,

  2. a temporary suspension of the processing of new applications for approval of installation functionality, and

  3. that the processing of applications already received for approval of the functionality of installations to be connected directly to the 420 kV grid is suspended.

The announcements have a significant impact on the future development of data centers in Norway, and we will monitor the developments closely. We find the following matters to be of special interest:

  1. How should different types of data centers be assessed – what should be prioritized or deprioritized?

  2. What will constitute socially critical consumption?

  3. What are the implications of the Norwegian Constitution for the proposed measures?

  4. What possibilities does the EEA Agreement provide?

  5. Should a distinction be made between new consumption and the expansion of existing consumption?

  6. What duration should the licenses have, and what will happen upon expiration?

  7. How should municipal zoning authority and the state licensing scheme be coordinated – will there be a municipal veto for data centers, as there is for onshore wind power?

Press releases from the Norwegian government and Statnett are available here:

Government seeks controlled growth of data centres in Norway - regjeringen.no

Midlertidige tiltak for fortsatt forsvarlig systemdrift | Statnett (in Norwegian only)